Sr.No Towers Work Description Progress 1 11 ...
Sr.No Towers Work Description Progress 1 1,2,3,4,...
Sr.No Towers Work Description Progress 1 1 ...
Sr.No Work Description Progress 1 Main Entrance Gate ...
...
Sr.No Towers Work Description Progress 1 7 ...
Sr.No Towers Work Description Progress 1 2 ...
. ...
Sr.No Towers Work Description Progress 1 1,2 ...
Sr.No Towers Work Description Progress 1 11,12 ...
Sr.No Towers Work Description Progress 1 ...
Super Structural Work of Tower 1,2,3,4,5,6,7,8,9,10 is completed. Finishing Work of Tower 1, 2, 3 Approximate 90%, Tower 4 Approximate 80% and Tower T...
Construction for Urban-67A has been started and work is in progress for 10 towers. As on date we have completed Rafting and shear wall work for Tower ...
We have completed super structure for tower no.1,2,3,4,5,6,7,8,9,10,11,12,14,15 & 16. In Tower No. 1,2,3 approx 86% of finishing work completed. T...
We have completed super structure for tower no.1,2,3,4,5,6,7,8,9,10,11,12,14,15 & 16. In Tower No. 1,2,3 approx 85% of finishing work completed. T...
We have completed super structure for tower no. 1,2,3,4,5,6,7,8,9,10. Working for commercial is already been started. Tower no.-1,2 & 3 appr...
We have completed super structure for tower no.1,2,3,4,5,6,7,8,9,10,11,12,14,15. Tower-16 is on 9th floor where Shuttering work is in progress. ...
We have completed super structure for tower no.1,2,3,5,8,9,10,11,12,14,15. Tower no. 4 is on 13th floor, Tower-6 is on terrace & Tower-7 is on 13t...
We have completed super structure for tower no.1,2,3,5,8,9,10,11,12,14,15. Tower no. 4 is on 9th floor, Tower-6 is on 12th floor & Tower-7 is on 9...
We have completed super structure for tower no. 1,2,3,5,6,4,8,9,10. Tower no. 7 is on 12th floor. Working for commercial is already been started. Towe...
We have completed super structure for tower no. 1,2,3,5,6,4,8,9,10. Tower no. 7 is on 9th floor. Working for commercial is already been started. Tower...
We have completed super structure for tower no.1,2,3,8,9,10,11,12,15. Tower no. 4 is on 7th floor, Tower-14 is on 12th floor completed, Tower- 5 is on...
We have completed super structure for tower no.1,2,3,5,6,4,8,9,10. Tower no. 7 is on 6th floor. Working for commercial is already been started. ...
We have completed super structure for tower no.1,2,3,8,9,10,11,12,15. Tower no. 4 is on 3rd floor, Tower-14 is on 12th floor, Tower- 5 is on 8th floor...
We have completed super structure for tower no.1,2,3,9,10,11,12,15. Tower no. 8 is on 11th floor, Tower-14 is on 10th floor, Tower 4 is on Ist floor, ...
We have completed super structure for tower no.1,2,3,5,6,4,8,9,10. Tower no. 7 is on 3rd floor. Working for commercial is already been started. ...
We have completed super structure for tower no.1,2,3,9,10,11,12,15. Tower no. 8 is on 11th floor, Tower-14 is on 7th floor, Tower 4 is on Ground floor...
We have completed super structure for tower no.1,2,3,5,6,4,8,9,10. Tower no. 7 is on 1st floor. Working for commercial is already been started. ...
Structure work in Tower no.-01,02,03,12 and 15 is completed. Now the work for Tower-08,09 and 14 is started. Tower no.- 10 is on 3rd floor and Tower n...
Structure work in Tower-1,Tower-2, Tower-3, Tower-8, Tower-9 & Tower-10 is completed till terrace. Tower no.4 is on 5th floor, Tower no-05 is on 4...